Project Name: Construction of the New Cruise Jetty in Tallinn Old City Harbour
Client: Port of Tallinn
Project Start: 04.2013
End of project: 04.2014
Description of Works: Main contracting for jetty construction. The following works are completed during the course of the project: piling works (199 pc), concrete works, dredging works (12300m3), communications for service of the vessels, total length of the jetty is 421 m;.